  • The 2007 Teams has made great progress in bringing us closer to our Grand opening in June of 2008.
    Check out the photo gallery with photos showing 2007 teams progress
  • November 2007
    Stucco interior and exterior of administration/classroom wings. Began roof tile on second home and the dining hall and classroom buildings.  Installed floor tile in the second house.
  • September 2007
    Stucco interior walls of second house and installed trusses on the administration/classroom wings.
  • July and August 2007
    The July and August teams Poured sub-flooring and installed rough plumbing and electrical for the second house. Completed footings, built walls and completed trusses for admin/classroom wings There were three teams in July and August from Colorado, New Jersey and Pennsylvania.
  • May and June 2007
    Completed exterior and interior walls, roof tiles and ceiling. Installed electrical and plumbing in first house and painted exterior of property walls. Completed trusses on second house.